Angus Energy (AIM: ANGS) is pleased to announce that , despite relatively slow progress in casing and cementing , it expects to resume drilling into the open hole section of the reservoir in the early part of next week with well clean-up operations set to commence on or around 16 th December shortly followed by well testing.
The drilling itself is expected to end on or around 14 December with the setting of the completion string (i.e. the production tubing). On this timetable, if there are no issues, the well can be declared a technical success by the middle of the month, although testing will be required before flow rates can be announced and a commercial success declared.
We have created an infographic video of the drilling process to assist in comprehension which is available under the video tab on our website and on our Twitter feed.
#Saltfleetby Sidetrack 🇬🇧 #ANGS
Stage 1 Preparation: Oct 21st – Nov 10th
2: Sidetrack Drilling: Nov 11th – 23rd
3: Casing Run: Nov 24th – Dec 4th
4: Open Hole Drilling: Dec 5th – 16th
5: Clean-Up: Dec 17th – 19th
6: Testing: Dec 20th onwards 🔥pic.twitter.com/YxwByAqFX9 https://t.co/AhgljsCRmo— Share_Talk ™ (@Share_Talk) December 3, 2022
Qualified Person’s Statement:
Andrew Hollis, the Technical Director of the Company, who has over 40 years of relevant experience in the oil and gas industry, has approved the information contained in this announcement. Mr Hollis is a Fellow of the Geological Society and a member of the Society of Petroleum Engineers.