Zephyr Energy PLC (AIM:ZPHR) 36-2 LNW-CC well – Drilling Operations Commenced

Zephyr Energy plc (AIM: ZPHR), the Rocky Mountain oil and gas company focused on responsible resource development and carbon-neutral operations , is pleased to announce that drilling operations have commenced on the State 36-2 LNW-CC well (the “well”) at its flagship project in the Paradox Basin, Utah, in the United States of America (“U.S.”) (the “Paradox project”).

Summary of drilling operations

Over the last week, CWC Ironhand Drilling Rig 118 (“Rig 118”) mobilised to the well-site, where it was subsequently assembled and tested. In addition, all necessary ancillary service providers arrived on site to support drilling operations.

The fully-funded well will target the Cane Creek reservoir, and drilling is planned to a total depth (“TD”) at 20,456 feet measured depth (9,598 feet true vertical depth) incorporating a 10,346 feet horizontal reservoir section. The well’s objective is to further delineate the Cane Creek reservoir beyond the productive State 16-2 LN-CC well and the nearby Federal 28-11 well (which was recently acquired by Zephyr and is currently shut-in due to infrastructure constraints, details of which were announced by the Company on 14 September 2022).

Drilling operations are expected to take approximately 30 days. After reaching TD and dependent on schedule and availability, a completion crew will subsequently be mobilised by the Company to hydraulically stimulate the horizontal portion of the well, immediately after which production testing shall commence. Further updates will be provided in due course.

Colin Harrington, Zephyr’s Chief Executive, said: “The commencement of drilling of the State 36-2 LNW-CC well is another landmark moment for the Company in its pursuit of unlocking the significant potential upside value from the Paradox project.

I’d like to thank our many partners and contractors who worked tirelessly through challenging conditions to meet our ambitious timeline following receipt of the final permit earlier this month. The focus now turns to drilling and operating in the safest and most effective manner possible, and I know this commitment is shared by all personnel on the drill site.

“While Zephyr’s primary objective for the well is to target production from the Cane Creek reservoir, we also plan to use the drilling operation to acquire important additional data from overlying reservoir targets.

“We look forward to keeping our stakeholders informed as drilling progresses over the coming weeks, and, as always, we will endeavour to operate in line with our core mission: to be responsible stewards of our investors’ capital and responsible stewards of the environment in which we work.”

Dawn rises over the CWC Ironhand Drilling Rig 118 at the State 36-2 LNW-CC well

Contacts

Zephyr Energy plc

Colin Harrington (CEO)

Chris Eadie (CFO)

Tel: +44 (0)20 7225 4590


Linking Shareholders and Executives :Share Talk

If anyone reads this article found it useful, helpful? Then please subscribe www.share-talk.com or follow SHARE TALK on our Twitter page for future updates. Terms of Website Use All information is provided on an as-is basis. Where we allow Bloggers to publish articles on our platform please note these are not our opinions or views and we have no affiliation with the companies mentioned

Weekly Newsletter

Sign up to receive exclusive stock market content in your inbox, once a week.

We don’t spam! Read our privacy policy for more info.

Tweet
WhatsApp
Email
Pocket
Share
Share