Oriole Resources cuts Bibemi gold project costs by 23% - Share Talk

Oriole Resources cuts Bibemi gold project costs by 23%

Oriole Resources plc (AIM: ORR) has identified a potential 23% reduction in initial capital expenditure at its Bibemi Gold Project in Cameroon, following a study of an alternative mineral processing method that could improve the project’s development economics.

The company, which holds a 50% interest in Bibemi, confirmed that independent consultant Stirling Process Engineering has completed a preliminary Scoping Study comparing ultra-fine grinding (UFG) with the previously proposed pressure oxidation (POX) processing method.

The UFG approach reduces estimated processing plant capital expenditure by 38%, from US$35.8 million to US$22.1 million, representing a saving of US$13.7 million.

This would lower total initial project capital expenditure from US$60.4 million to US$46.7 million, while maintaining the planned annual gold production target of approximately 10,000 ounces.

The revised processing method uses flotation followed by ultra-fine grinding and leaching, avoiding the technically complex and capital-intensive autoclave equipment required for pressure oxidation.

The simpler design could reduce operational complexity and financing requirements, although the study indicates slightly higher operating costs per ounce of gold recovered.

Estimated project operating costs increase from approximately US$575 to US$617 per ounce, reflecting lower gold recovery and higher assumed power costs.

Gold recovery under the UFG method is estimated at 78.7%, compared with 85% under POX, while annual processing throughput increases approximately 9% to 207,956 tonnes.

Despite the lower recovery rate, both scenarios target similar annual gold output, with the higher throughput helping compensate for the difference.

The estimates remain preliminary, with Scoping Study cost accuracy of approximately plus or minus 30%. The two processing assessments also use different power price assumptions.

Further optimisation could improve recoveries and reduce processing costs, particularly through adjustments to flotation, leaching conditions and reagent consumption.

Oriole is considering ways to reduce cyanide and lime requirements, while additional work by ALS in Australia is assessing whether more gold can be recovered from flotation tailings.

Chief Executive Martin Rosser described the findings as encouraging, highlighting the potential financing and operational advantages of the alternative processing route.

He said the results would be incorporated into an updated Preliminary Economic Assessment (PEA), which could demonstrate improved project economics compared with the previous development scenario.

The updated assessment will also consider revised mining costs, increased processing throughput, lower recovery assumptions and changes to the mine schedule.

Bibemi currently hosts a JORC-compliant Mineral Resource of 6.96 million tonnes grading 2.06 grams per tonne gold, containing approximately 460,000 ounces.

Of this total, 100,000 ounces are classified as Indicated, with the balance in the lower-confidence Inferred category.

The proposed initial development centres on an optimised open-pit scenario targeting approximately 89,000 ounces of gold over a seven-year mine life, with average annual production of around 10,000 ounces.

These figures are based on preliminary technical studies and do not represent a declared Ore Reserve or an approved production plan.

The company has also identified a separate conceptual Exploration Target of 145,000–400,000 ounces, although further drilling would be required before any of this material could potentially be incorporated into a formal Mineral Resource.

Oriole has submitted an Exploitation Licence Application for Bibemi, and the latest processing results are expected to support ongoing discussions with the Cameroonian authorities.

The company believes that reducing initial development costs could make the proposed mine more attractive to potential financing partners.


Linking Shareholders and Executives :Share Talk

If anyone reads this article found it useful, helpful? Then please subscribe www.share-talk.com or follow SHARE TALK on our Twitter page for future updates. Terms of Website Use All information is provided on an as-is basis. Where we allow Bloggers to publish articles on our platform please note these are not our opinions or views and we have no affiliation with the companies mentioned