Empyrean Energy PLC (AIM:EME) Projects Update

 

Empyrean Energy plc, the oil and gas development company with interests in China, Indonesia and the United States, is pleased to announce the following update on operations:

Share Talk spoke with Gaz Bisht last month, independent consultant to Empyrean Energy Plc (AIM:EME). He provides valuable insight into the unique near time 3D acquisition strategy of the company. He also updated listeners on the timescales and hopes of the data acquisition and how this fits in with the strategy of the company.

Block 29/11 China

The Company’s 3D seismic acquisition programme is progressing well with approximately 1/3 of the acquisition complete. The data collected so far has been of good quality.

Mako South-1 well Duyung PSC Indonesia

The company has been advised by Conrad Petroleum that the COSL Seeker jack-up rig has arrived on location for the drilling of the Mako South-1 well and is presently continuing to rig up in preparation for drilling operations to commence within days. A further announcement will be made when rigging up is complete and drilling operations commence.

Sacramento Basin Assets

Empyrean advises that Sacgasco Limited (“Sacgasco”) is in the final stage of finalising the Farm-in Agreement and JOA documents. As announced 15 June 2017 Empyrean was required to pay US$10,000 upfront and then a further US$90,000 (collectively “the Dempsey Deposit”) upon signing the Farm-in and JOA documents for the Dempsey Prospect and a further US$20,000 (“the Alvares Deposit”) to reimburse Sacgasco for back costs and leasing of the Alvares Prospect.

In addition, Empyrean was required to pay US$1,500,000 by 17 June 2017 (“the Dempsey Consideration”) towards dry hole costs (i.e. up to the point of testing and running production casing or abandonment) of the Dempsey-1 Well to earn its 25% Working Interest in the Dempsey Prospect.

If the Dempsey-1 Well costs exceed US$3,200,000 then Empyrean will pay 25% of any further costs under standard JOA terms. Empyrean has paid US$10,000 under its agreement so far and Sacgasco have agreed that Empyrean will pay the balance of US$90,000 for the Dempsey Deposit and US$20,000 for the Alvares Deposit within 3 working days of signing the definitive Farm-in Agreement and JOA documents. Furthermore, it has been agreed that Empyrean will pay US$1,500,000 for the Dempsey Consideration after the definitive Farm-in Agreement and JOA has been signed and within 5 working days of a cash call by Sacgasco to Empyrean prior to the drilling of the Dempsey-1 Well.

Empyrean is fully funded to make the payments for the Dempsey and Alvares Deposits and Dempsey Consideration above.

Linking Shareholders and Executives :Share Talk

If anyone reads this article found it useful, helpful? Then please subscribe www.share-talk.com or follow SHARE TALK on our Twitter page for future updates.

Terms of Website Use

All information is provided on an as-is basis. Where we allow Bloggers to publish articles on our platform please note these are not our opinions or views and we have no affiliation with the companies mentioned

Malcare WordPress Security