Union Jack Oil PLC (UJO.L) West Newton Community Update

Union Jack Oil plc (AIM: UJO), a UK focused onshore hydrocarbon production, development and exploration company, notes that Rathlin Energy (UK) Limited (“Rathlin”), the Operator of PEDL183, communicated the following to local residents as part of its participation in the West Newton Community Liaison Group.

Union Jack holds a 16.665% interest in this licence, containing the West Newton A-1 discovery well and the recent successful West Newton A-2 conventional appraisal well.

“We hope you and your families are safe, healthy and managing under the current circumstances.

This update is to let you know that we are moving our programme of works forward, in line with the

latest government and public health guidance on Covid-19. We continue to follow the advice closely.

Image 1 300x225 - Union Jack Oil PLC (UJO.L) West Newton Community Update

West Newton A
We secured a permit variation from the Environment Agency on Friday 24 April 2020. This enables us to

recommence our well test using a pumpjack (nodding donkey) and a smaller incinerator unit. Once the

required personnel and equipment are available the testing operations will recommence.

West Newton B
Pre-construction works started during the week commencing 6 April 2020. To date, additional land

drainage has been installed in the affected fields. Two water monitoring boreholes, which are a condition

associated with our West Newton B Environment Agency permit, have also been installed and baseline

sampling will be undertaken.

On 4 May 2020, work commenced on the construction of the West Newton B access track. This activity is

the subject of an archeological watching brief and is expected to take five to six weeks.

Road closures, agreed by East Riding of Yorkshire Council, have been instated for safety reasons on

Pasture Lane. Our traffic management plan for the construction phase of operations is now in effect and

works are restricted to Monday to Saturday between the hours of 07:00 and 18:00.

In due course, site construction works will commence on the West Newton B drilling site. This work will

include a full archeological strip, map and record study, following which, site construction will begin. The

site construction works are anticipated to take between five and six weeks.

Drilling of the West Newton B-1 well will commence following the completion of the access track and site

construction activities and the conductor setting operations.

During the course of these operations, we will keep our community neighbours informed of our activities

through website updates, the West Newton Liaison Committee and other periodic notices. We are, of

course, available to address any questions or concerns.”

For further information, please contact:

Union Jack Oil plc +44 (0)78 0154 0358

David Bramhill


Linking Shareholders and Executives :Share Talk

If anyone reads this article found it useful, helpful? Then please subscribe www.share-talk.com or follow SHARE TALK on our Twitter page for future updates.

Terms of Website Use

All information is provided on an as-is basis. Where we allow Bloggers to publish articles on our platform please note these are not our opinions or views and we have no affiliation with the companies mentioned

UJO REPLACE - Union Jack Oil PLC (UJO.L) West Newton Community UpdateUJO REPLACE - Union Jack Oil PLC (UJO.L) West Newton Community Update
Share via
Copy link
Malcare WordPress Security