Synergia Energy Limited announces the following update regarding its Cambay PSC (WI: 50%), onshore India.
Selan Exploration Technology Limited (“Selan”) have informed the Company of the following planned activities on the Cambay PSC:
· The Aakash 50T work over rig will be deployed to the Cambay C-64 wellsite by mid-September to undertake the installation of the sucker rod pump.
· Selan plan to deploy a drilling rig contracted from Kiri Oilfield Services to drill a new well on the Cambay PSC in October 2025. The cost of the new well will be carried by Selan under the work program associated with the Farm In / Farm Out agreement between Synergia and Selan.
For and on behalf of Synergia Energy Limited
Roland Wessel
CEO
For further information, please contact:
|
Investor Enquires Synergia Energy Ltd Briana Stayt Investor Relations Email: bstayt@synergiaenergy.com Tel: +61 8 9485 3200 Australia |