Synergia Energy Limited has released an operational update on its Cambay PSC activities, highlighting steady progress across both production wells and the current drilling programme.
At the C-64 well, recent workover operations have lifted output to an average of 30 bopd. The C-72 well remains in the brine-clearance phase, with production updates expected once the operation is complete. Meanwhile, the C-74 workover has concluded, with a sucker rod pump installed and preparations underway for the well to enter production.
The Aakash rig has now been mobilised to the C-19z well, where a clean-up operation is being initiated.
In drilling activity, the C-78 well has reached a total depth of 1,827 metres, successfully intersecting the targeted OSII formation at 1,745 metres. Logging operations are currently in progress.
Synergia said further updates will be provided as the programme advances across its multi-well campaign.
Roland Wessel
CEO
For further information, please contact:
|
Investor Enquires Synergia Energy Ltd Briana Stayt Investor Relations Email: bstayt@synergiaenergy.com Tel: +61 8 9485 3200 Australia |