Premier African Minerals Limited is pleased to provide this update on the plant status and flotation plant test run at Zulu Lithium and Tantalum (“Zulu”) following the installation of spodumene float section inserts. As previously announced, the purpose of the installation and commissioning of the inserts is to reduce the retention time of concentrates in the cleaner section of the original float plant and in so doing, improve grade and recovery (full details of which were announced on 17 October 2024).
|
Highlights |
|
|
Ø |
Installation of spodumene float section inserts complete. |
|
Ø |
Plant restarted on 6 July 2025. |
George Roach, CEO, commented; “Thanks to the outstanding support we have received from each of the OEM suppliers associated with all the plant components from the mill to final floatation, we have been able to restart the plant late afternoon on 6 July 2025.
The plant has run with limited feed to allow for checks on the operation of each of the plant components and process integration up to the spodumene cleaner cell inserts that will be brought into the process today once sealants have hardened.
All being well, ore from the ROM pad will be fed from today and commissioning and optimisation of the Primary Spodumene Floatation Plant will follow.
Preliminary results and progress updates at Zulu will follow once they become available and have been properly validated.”
Market Abuse Regulations
The information contained within this announcement is deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014 as it forms part of UK Domestic Law by virtue of the European Union (Withdrawal) Act 2018 (“UK MAR”).
The person who arranged the release of this announcement on behalf of the Company was George Roach.
A copy of this announcement is available at the Company’s website, www.premierafricanminerals.com.
Enquiries:
|
George Roach |
Premier African Minerals Limited |
Tel: +27 (0) 100 201 281 |