Oilex Limited (Oilex or the Company) is pleased to announce the following update with respect to its operations in India.
C-77H Re-frac Operations Update
All of the equipment necessary for the re-frac operation has arrived onsite with the exception of the coiled tubing unit (CTU) which has been delayed by monsoon season-related rain. The CTU is expected to arrive onsite tomorrow after which the initial stage of the re-fraccing operation, perforating the zones to be hydraulically fractured, will commence.
The actual fraccing operation is anticipated to last 7 days and will be followed by flow-back and testing. We currently expect to be able to announce the results of the re-frac operation in August 2022.
For and on behalf of Oilex Ltd
Roland Wessel
Managing Director