Kazera Global plc (AIM: KZG) has outlined plans to progressively ramp up production at its Walviskop heavy mineral sands operation in South Africa to approximately 30,000 tonnes of heavy mineral concentrate (HMC) per month.
The operational planning is being undertaken with South Africa AT Investments (SAI), with production currently scheduled to commence in early 2027. Plant and equipment is being mobilised and is expected to arrive in South Africa during November 2026.
A comprehensive Mine Plan remains under development, but Kazera subsidiary Whale Head Minerals has prepared an interim plan covering the plant and equipment required for the operation.
Current estimated Free on Truck sales prices for HMC are around US$165-US$170 per tonne.
At the targeted 30,000-tonne monthly production rate, this would imply gross monthly sales of approximately US$4.95 million to US$5.1 million, before operating costs and subject to production and realised pricing.
Interim Chief Executive Richard Jennings said achieving the targeted production rate at current prices would “totally transform” the future cash flow profile of the company’s Whale Head Minerals subsidiary.