title: "Georgina Energy completes key equipment orders ahead of Hussar drilling"
publisher: "Share Talk"
author: "sharetalk"
published: "2026-11-16T08:53:01+00:00"
modified: "2026-11-16T08:53:01+00:00"
date: 2026-11-16
canonical: "https://www.share-talk.com/georgina-energy-completes-key-equipment-orders-ahead-of-hussar-drilling/"
category: "Energy"
categories: ["Energy"]
tags: ["Amadeus Basin", "Anthony Hamilton", "Australia", "Ensign Energy Drilling", "Georgina Energy", "GEP", "GEX", "Harlequin Energy Ltd", "Helium", "Hussar-2 well", "hydrogen", "Mark Wallace", "Mining Minerals & Metals Plc", "MMM", "natural gas", "Northern Territory", "seismic approval process", "Western Australia"]
image: "https://i0.wp.com/www.share-talk.com/wp-content/uploads/2026/11/040e7571-da2f-4eb1-b62b-59069cd8065c.png?fit=1727%2C911&quality=80&ssl=1"
format: "news"
language: "en-GB"
---

# Georgina Energy completes key equipment orders ahead of Hussar drilling

**Published:** November 16, 2026
**Author:** sharetalk
**Categories:** Energy
**Tags:** Amadeus Basin, Anthony Hamilton, Australia, Ensign Energy Drilling, Georgina Energy, GEP, GEX, Harlequin Energy Ltd, Helium, Hussar-2 well, hydrogen, Mark Wallace, Mining Minerals & Metals Plc, MMM, natural gas, Northern Territory, seismic approval process, Western Australia
**Featured image:** ![](https://i0.wp.com/www.share-talk.com/wp-content/uploads/2026/11/040e7571-da2f-4eb1-b62b-59069cd8065c.png?fit=1727%2C911&quality=80&ssl=1)

---

[Georgina Energy Plc (LON: GEX)](https://www.investegate.co.uk/announcement/rns/georgina-energy-plc--gex/hussar-ep513-equipment-procurement-/9875801) has completed the ordering of all long-lead drilling equipment for its Hussar EP513 project in Western Australia, marking a further operational milestone as the company prepares to drill a well targeting helium, hydrogen and natural gas.

The company confirmed that it has ordered the casing, tubing, cementing and float equipment required for the Hussar well, following its earlier procurement of wellhead equipment from **Cactus Wellhead on 6 November 2026**.

**All major long-lead equipment is now on order**, with the next critical step involving mobilisation of the contracted **Ensign 970 drilling rig** to the wellsite.

Ensign has been notified to mobilise the rig, although the precise drilling commencement date remains subject to safe transportation and final preparations.

**The Hussar well is planned to reach approximately 3,200 metres and is expected to require around 50 days of drilling.**

The latest orders include approximately **3,200 metres of surface, intermediate and production casing**, alongside production tubing and a VersaFlex expandable liner hanger system.

Additional equipment includes float shoes, float and landing collars, cement plugs, centralisers and stop collars, which are required to secure the wellbore and maintain integrity throughout drilling.

Ordering these components in advance allows Georgina to coordinate equipment deliveries with rig mobilisation and reduce the risk of delays once operations begin.

**Civil engineering and wellsite preparation works at Hussar EP513 have been completed**, leaving rig transportation and installation among the principal remaining operational requirements.

However, access arrangements continue to present logistical challenges.

The company is working with contractors to improve the **Eagle Highway access route from the Mangkili turn-off on the Gunbarrel Highway** to the Hussar location.

Weather-related road restrictions have affected mobilisation planning, and Georgina is prioritising the safe movement of personnel and heavy equipment.

**A revised drilling commencement date will be announced once mobilisation arrangements are confirmed.**

Chief Executive **Anthony Hamilton** said the latest procurement represented an important step towards drilling, with the company continuing to work closely with contractors to complete preparations.

He reiterated that drilling Hussar and evaluating its potential helium, hydrogen and natural gas resources remain Georgina’s principal operational priorities.

Alongside drilling preparations, **Georgina has submitted formal applications for a proposed seismic survey at Hussar** to Western Australia’s Department of Mines, Petroleum and Exploration.

The programme is expected to involve approximately **30 days of fieldwork**, using lightweight seismic equipment intended to minimise environmental disturbance.

Unlike the drilling operation, the seismic survey will not require heavy vehicle access, potentially allowing work to proceed independently of the rig mobilisation process.

However, **the survey remains subject to regulatory and Traditional Owner cultural heritage approvals**, while the company is finalising the programme budget.

Georgina intends for the seismic work to be funded by **Harlequin Energy**, although the final funding arrangements have not yet been confirmed.

**Hussar’s exploration potential is supported by an independent geological report dated 1 February 2026**, which estimates net attributable, unrisked 2U prospective resources of **283 billion cubic feet of helium, 315 billion cubic feet of hydrogen and 2.93 trillion cubic feet of hydrocarbon gas**.

These estimates were prepared under the SPE Petroleum Resources Management System and represent prospective volumes rather than discovered or commercially recoverable reserves.

Using its assumed commodity prices, Georgina has calculated a combined **theoretical in-situ value of approximately US$152 billion** for the estimated resources.

**That figure is not a project valuation, revenue forecast or estimate of recoverable economic value.** It is based on unrisked prospective volumes and excludes drilling, production, gas separation, processing, infrastructure and transportation costs.

There is also no certainty that the targeted resources will be discovered or commercially produced.

The planned Hussar well will therefore be important in establishing the presence, composition and potential deliverability of the gases identified in the geological assessment.

**For Georgina Energy, completing long-lead equipment procurement reduces a significant element of drilling preparation risk**, although operational execution remains dependent on rig mobilisation and suitable site access.

The company’s next milestones include **confirmation of the Ensign 970 rig’s arrival, announcement of the revised spud date and progress on seismic approvals**.

Successful drilling would provide the geological and technical information required to evaluate Hussar’s potential, with particular interest in the project’s exposure to helium and naturally occurring hydrogen.

**The immediate focus is now shifting from procurement and site preparation to the physical mobilisation of the drilling rig**, as Georgina moves towards testing one of its principal Australian exploration prospects.

---