{"id":95520,"title":"Angus Energy PLC (AIM:ANGS) Update on installation schedule at Saltfleetby","publisher":"Share Talk","author":"sharetalk","published":"2022-04-08T12:51:59+00:00","modified":"2022-04-08T12:51:59+00:00","canonical_url":"https://www.share-talk.com/angus-energy-plc-aimangs-update-on-installation-schedule-at-saltfleetby/","markdown_url":"https://www.share-talk.com/angus-energy-plc-aimangs-update-on-installation-schedule-at-saltfleetby.md","json_url":"https://www.share-talk.com/angus-energy-plc-aimangs-update-on-installation-schedule-at-saltfleetby.json","category":"Energy","categories":["Energy"],"featured_image":"https://i0.wp.com/www.share-talk.com/wp-content/uploads/2023/11/Stencil-Google-Chrome-2023-04-19-at-2.47.43-PM.jpeg?fit=1231%2C615&quality=89&ssl=1","format":"news","language":"en-GB","content":"The Company updates on progress on its installation and commissioning schedule. Additional noise abatement and other modifications has occasioned some small delay in the arrival of the compressor skid but with no impact on overall timeline.\n\nRemaining civil engineering is limited to bunding works around select skids and tanker offtake areas. Welding continues at pace, with some 500 butt-welds now completed.\n\nDry commissioning is expected to begin on 26 April with select hydrotesting of key site pipework. This will be augmented with electrical and control tests during early May. Wet commissioning is expected to begin at or around 15 May and is expected to last approximately two weeks. The Company continues to target First Gas by 1 June allowing for one full month of unhedged production.\n\n \n\n \n\n|   |   |   |   |\n| --- | --- | --- | --- |\n| Skid/Unit | Basc Fabrication Status | Blasting, Painting Assembly, Testing, Certification etc | Target Delivery Date |\n| Metering Package | 100% complete | Completed | Completed |\n| Analysis Package | 100% complete | Completed | Completed |\n| Compressor Coolers | 100% complete | Completed | Completed |\n| Condensate Tanks | 100% complete | Completed | Completed |\n| Water Storage Tanks | 100% complete | Completed | Completed |\n| Flare Package | 100% complete | Installed | Completed |\n| Fuel Gas Skid | 100% complete | Completed | Completed |\n| Flare Knock Out Skid | 100% complete | Completed | Completed |\n| Electrical Room | 100% complete | Verification | 12 April |\n| Separator Vessel | 100% complete | Verification | 12 April |\n| Passive Dehydration | 100% complete | Re-assembly | 20 April |\n| 1st compression | 100% complete | Re-assembly | 21 April |\n| Joule Thomson Skid | 100% complete | Re-assembly | 26 April |\n| Export Filters/Diverters | >90% complete | Re-assembly | 26 April |\n| Gas Engine Generator | 90% complete | Exhaust manifold, sound insulation | 29 April |\n| Condensate Stabilisation Skid | 100% complete | Reassembly | 5 May |\n\nEND.\n\nEnquiries:\n\nAngus Energy Plc\n\n[www.angusenergy.co.uk](http://www.angusenergy.co.uk)\n\nGeorge Lucan\n\nTel: +44 (0) 208 899 6380"}