Angus Energy (AIM: ANGS) is pleased to announce the completion of almost all electrical connections and all instrument
connections excepting storage and drain areas. Moreover, input/ output testing between the control computer or SCADA and each of the site’s 80+ instruments and actuated valves which that SCADA governs is complete.
Input/ output testing on the remaining electrically powered systems including re-boilers, switchgear, air compressors and lighting is expected to conclude on Wednesday (20th July) when system-wide testing of the SCADA begins.
We expect to introduce live gas as far as the test separator on Friday (22nd July) as part of the commissioning schedule and will advise further on a precise date for export and nominations thereafter.