Alien Metals Limited (UFO.L) Capstone to commence drill program at Donovan 2

Capstone to shortly commence 2,500m drill program at Donovan 2 Cu-Au Project

Follow the link to view the announcement in full including all figures:

http://www.rns-pdf.londonstockexchange.com/rns/4655L_1-2021-1-12.pdf

Alien Metals Ltd (AlienMetals or the Company), a minerals exploration and development company, is pleased to announce that since executing the earn-in agreement (Agreement) with Capstone Mining Corp (Capstone) (TSX: CS) over its Donovan 2 Copper-Gold project (the Project) in Mexico (Transaction), Capstone have completed their initial 2020 obligation of exploration expenditures and will advance to the next phase of the Agreement.

Pursuant to the terms of the Agreement, Capstone can acquire a 65% interest in Donovan 2 through committed expenditure and cash payments totalling ~US$3.9million. Capstone can move to an 80% interest in the Project through free-carrying Alien to completion of a prefeasibility study.

The core of the work carried out by Capstone in late-2020 was to complete a detailed close spaced surface Induced Polarisation (IP) geophysical survey across the majority of the tenement, as announced by Alien Metals on 13 November 2020, to both add infill detail to the northern anomaly already defined by Alien and as an extension to historic geophysical work undertaken by Alien. This work was successfully completed in December 2020 with the final reporting and interpretation currently being completed.

Capstone have indicated that they have planned an initial 2,500m drilling program as part of their required $450,000 USD expenditure commitment for 2021. Drill locations will be finalised following interpretation of the IP report, with provisional planning well underway.

Bill Brodie Good, CEO & Technical Director of Alien Metals, commented:

“The Company is extremely encouraged by the speed of progress by the Capstone technical team, who mobilised quickly in an effort to drive exploration of the project. Capstone considered that commissioning a more detailed ground IP survey to compliment historic work undertaken by Alien while awaiting the necessary drill permitting would refine or reaffirm the existing drill targets.

Capstone have been managing the main elements of the program while Alien provide the necessary early stage on the ground support. We are looking forward to some positive results from this work.

Alien has managed to get the previous drilling permit granted on Donovan 2 at the end of 2020, and with Capstone now ready to move into the next phase of the earn-in agreement, drilling can finally start to fully test what we see as an exciting copper-gold VMS system. Given the location of Donavan 2, near to existing infrastructure and operating mines, if Capstone are successful in identifying a commercial deposit it is well placed for rapid advancement.”

Figure 1: Location of Donovan 2 Project, Zacatecas Region, Mexico in relation to Capstone Mining’s Cozamin Copper/Silver Mine and the Teck San Nicolas VMS Copper deposit.

The IP survey was completed for 27.3 line kilometres and the data capture took 24 days. The IP survey was carried out by Zonge International of Arizona, USA, who have extensive experience of working in Mexico. The work was completed in late December 2020 with no reportable safety or environmental incidents and Capstone as agreed kept Alien updated on every step of the work with the Alien team offering support as required.

An initial review of the provisional data generated by this IP survey appear to confirm and extend upon the anomalies that Alien had identified in the north and east-central areas of Donovan 2. Additional new features are also observed along the western and southern limits of the license. The original drill plan designed by Alien may be subject to change upon Capstone’s review of the finalised geophysical data.

Figure 2: Donovan 2 provisional resistivity 2D inversion sections in a 3D view looking north, Capstone, January 2021

Figure 3: Donovan 2 provisional chargeability 2D inversion sections in a 3D view looking north, Capstone, January 2021

Alien are looking forward to the final interpretation and results of this programme and to the next stage of work at Donovan 2 and are delighted with the work and engagement of Capstone in all aspects.

The Board of Alien continues to assess a range of mineral projects and opportunities, with particular focus on exploration projects with significant exploration and value upside.

For further information please visit the Company’s website at www.alienmetals.uk


Linking Shareholders and Executives :Share Talk

If anyone reads this article found it useful, helpful? Then please subscribe www.share-talk.com or follow SHARE TALK on our Twitter page for future updates. Terms of Website Use All information is provided on an as-is basis. Where we allow Bloggers to publish articles on our platform please note these are not our opinions or views and we have no affiliation with the companies mentioned

Weekly Newsletter

Sign up to receive exclusive stock market content in your inbox, once a week.

We don’t spam! Read our privacy policy for more info.

Tweet
WhatsApp
Email
Pocket
Share
Share