Critical Metals plc (LON: CRTM) has reported encouraging preliminary metallurgical results from its Molulu Copper-Cobalt Project in the Democratic Republic of Congo, achieving 74.13% copper recovery from stockpiled material.
The London-listed mining company completed the acid-soluble copper testing programme in collaboration with a potential offtake partner, providing initial evidence that copper contained in existing stockpiles could be extracted using acid-based processing methods.
300 kilograms of stockpiled ore were tested, with the blended sample returning a head grade of 1.43% total copper and an acid consumption figure of 3.91, although the announcement did not specify the units for the latter measurement.
The findings support further investigation of hydrometallurgical processing at Molulu, including potential heap leaching and solvent extraction-electrowinning (SX-EW).
Acid leaching is commonly used to extract copper from oxide and certain secondary copper minerals, offering an alternative to conventional flotation where mineralogy and operating economics are suitable.
However, the preliminary laboratory results do not establish the performance achievable in a commercial operation. Further work will be required to assess processing conditions, acid consumption, recovery times and the consistency of mineralisation across the stockpiles.
The programme will also help Critical Metals distinguish between oxide, transitional and primary sulphide mineralisation, supporting future processing decisions and mine planning.
Chief Executive Danilo Lange said the results had met the programme’s initial objective, describing the involvement of a potential offtake partner as encouraging for the project’s development prospects.
He acknowledged that additional technical studies and independent verification would be necessary before Molulu’s commercial potential could be established.
Critical Metals plans to continue discussions with the prospective offtake partner while advancing its exploration and geological modelling activities.
The next phase includes further three-dimensional block modelling, incorporating historical exploration information and current quality assurance and quality control data.
The company also intends to prepare a preliminary extraction schedule, commission an independent third-party review and identify additional priority exploration targets.
Follow-up drilling will assess potential extensions of the known mineralisation, with results contributing to updated geological models and future development studies.
No binding offtake agreement, commercial production timetable or definitive economic assessment has been announced.
The results provide an encouraging technical foundation for advancing Molulu, although the limited sample size means further testing will be essential before conclusions can be drawn about the wider deposit.
The next milestones will be additional metallurgical work, updated resource modelling and progress towards establishing an economically viable processing strategy, alongside continued engagement with potential commercial partners.