Pulsar Helium Inc. (AIM/TSXV: PLSR) has signed and accepted a firm proposal from Chart Energy & Chemicals, part of Baker Hughes, covering major processing equipment for its proposed Rare Gas Hub in Minnesota.
The package has an aggregate equipment-supply value of US$85.5 million and covers both a commercial-scale helium purification and liquefaction plant and a carbon dioxide processing plant.
The proposed helium system would have nameplate liquefaction capacity of 861 litres per hour, equivalent to approximately 7.5 million litres of liquid helium annually at continuous nameplate operation, or around 200 million standard cubic feet of gaseous helium.
The CO2 system is designed for 300 tonnes per day of capture capacity, although storage, loading and certain supporting infrastructure are outside the current scope.
Pulsar is required to make a US$5.025 million first payment following signing and TSXV approval. The company said this will be funded from its existing US$25.2 million cash balance.
That initial payment includes US$750,000 under the existing Limited Notice to Proceed, with the full US$1 million committed under the LNTP credited against future proposal payments.
The next major payment is US$8.55 million, scheduled for 31 January 2027, and is subject to Pulsar obtaining further funding.
Payment of this second milestone would authorise Chart to begin procurement of long-lead items.
If the US$8.55 million payment is not made by that date, the project automatically enters a suspension period of up to 180 days. During that period, the reserved helium liquefaction equipment remains protected and Pulsar has no obligation to make the second payment.
Manufacture of the main equipment is expected to take approximately two years following receipt of the second milestone payment, although some helium liquefaction equipment covered by the proposal has already been manufactured.
Importantly, the US$85.5 million figure is not the total installed cost of the Rare Gas Hub. It excludes taxes, duties and tariffs, installation, commissioning, site infrastructure, interconnections and various owner and third-party costs.
Pulsar is therefore continuing to evaluate financing options both for the remaining Chart milestone payments and for the wider capital expenditure required to build and commission the facility.
The company is separately progressing discussions over a proposed site in Lake County, Minnesota, but no definitive site agreement has yet been completed. Any acquisition or lease remains subject to due diligence, utility suitability, permits and other approvals.
For investors, signing the Chart proposal significantly advances Pulsar from conceptual plant planning towards defined commercial-scale processing infrastructure. The central financing question, however, is now much clearer: Pulsar must secure capital for the US$8.55 million January milestone, the remaining US$85.5 million equipment programme and the additional costs required to turn that equipment into an operating plant.