88 Energy Limited (ASX:AIM:88E) Hickory-1 Exploration Well – Rig Contract Executed

Highlights

· Rig contract executed for drilling of the Hickory-1 exploration well

· Permitting and planning remain on track for scheduled spud in late-February / early-March 2023

· Hickory-1 designed to appraise six key reservoir targets and 647 million barrels of oil1,2

· Icewine East renamed Project Phoenix to reflect the new focus on proven oil-bearing conventional reservoirs

· Project Phoenix unit application open for public comment, closing 31 December 2022

88 Energy Limited (ASX:88E, AIM:88E, OTC:EEENF) ( 88 Energy or the Company ) is pleased to announce that it has executed a rig contract with Nordic-Calista LLC ( Nordic ) for the use of their Rig-2 to drill the Hickory-1 exploration well on the Alaskan North Slope.

Hickory-1

The Hickory-1 well is designed to appraise six conventional reservoir targets within the SMD, SFS, BFF and KUP reservoirs and 647 million barrels of oil1,2, with spud scheduled for late-February / early-March 2023 to a permitted total depth of 12,500 feet. The Hickory-1 well has been significantly de-risked by recent drilling and flow tests carried out on adjacent acreage by Pantheon Resources, the interpretation of the Icewine-1 well logs, the modern Franklin Bluffs 3D seismic data ( FB3D) and AVO analysis.

An optimal drilling location has been selected adjacent to the Dalton Highway using the above data. This location intersects and will test the substantial potential oil volumes noted across all mapped play fairways, and in particular the SMD, SFS and BFF reservoirs.

Significant progress has been made on permitting and planning of Hickory-1 by our appointed project manager, Fairweather, LLC. All long lead items have been secured and tendering is nearly complete.  Further details of the drilling program and schedule will be announced by the Company in the lead up to planned spud, which remains subject to relevant government and other approvals.

Project Phoenix

The Icewine East area has been renamed Project Phoenix to reflect the Company’s refreshed exploration strategy for this acreage. Since its acquisition in 2014, the acreage targeted the unconventional HRZ play. Project Phoenix is now focused on the proven oil-bearing conventional reservoirs that were identified during the drilling and logging of Icewine-1 and 2, and more recently that were flow tested by Pantheon Resources. Project Phoenix is strategically located on the Dalton Highway with the Trans-Alaska Pipeline System running through the acreage.

The Company has put forward a unit application covering the Project Phoenix acreage and received notice from the Alaska Department of Natural Resources ( DNR ) that the application is open for public comment until 31 December 2022. The DNR will consider any comments and issue a decision no later than 1 March 2023. The unit approval will extend the leases for Project Phoenix beyond their primary term and provides an agreed program to assess commercialisation of the acreage and a pathway to development and production. 

1 Cautionary Statement: The estimated quantities of petroleum that may be potentially recovered by the application of a future development project relate to undiscovered accumulations. These estimates have both an associated risk of discovery and a risk of development. Further exploration, appraisal and evaluation are required to determine the existence of a significant quantity of potentially movable hydrocarbons.

2 Mean unrisked resource – Net Entitlement to 88 Energy. Refer announcement released to ASX on 23 August 2022

About Nordic and Rig-2

Nordic

Nordic Calista, a wholly owned subsidiary of Calista, has been operating custom build arctic rigs since 1985. Founded in 1972, Calista Corporation (Calista) is one of the largest of the 13 regional corporations in the state of Alaska.

Rig-2

Rig-2 is a single module, self-propelled drilling rig. The unique single module design eliminates extended rig up/down providing significant efficiencies during the winter exploration season. Rig-2 incorporates a 464k lbs triple mast with a 600HP AC top-drive.

This announcement has been authorised by the Board.

Media and Investor Relations

88 Energy Ltd

[email protected]

Ashley Gilbert, Managing Director

Tel: +61 8 9485 0990

Finlay Thomson, Investor Relations

Tel: +44 7976 248 471


Linking Shareholders and Executives :Share Talk

If anyone reads this article found it useful, helpful? Then please subscribe www.share-talk.com or follow SHARE TALK on our Twitter page for future updates. Terms of Website Use All information is provided on an as-is basis. Where we allow Bloggers to publish articles on our platform please note these are not our opinions or views and we have no affiliation with the companies mentioned

Weekly Newsletter

Sign up to receive exclusive stock market content in your inbox, once a week.

We don’t spam! Read our privacy policy for more info.